Second Floor framing looks complete and the house ensclosing has started.  I walked around the whole house to see how well they were butting up the panels... I could see lots of daylight between some of the panels.  I'll ask the PM if they can use some expanding foam to fill those up as I do not think the house wrap would suffice.  I also noticed that a water meter has been installed for the property.  

Anyone experience these gaps between the paneling?  And did they fix it?

Day 46

Day 46 Selfie

Water meter installed

Loft still requires panels



A whole lotta daylight between the panels on the second floor



How is this fixed?  Expanding Foam?